Best Builders /
Best Builders /
National Hosting Authority,
- Honiara, Solomons Islands : National Hosting Authority 2022 - 2023
Payment 1 - 20% Mobilization Payment for Labor based Contract
Payment 2 - 35% Payment for 50% of work
Payment 3 - 35% For completion of work
Payment 4 - 10% Retention
Labour Based Contract for Upgrade of Games Village for Pacific Games 2023 - GTB-GFC 09/22.
Lot 2 -King George Sixth National Secondary School Carpentry Works for Girls Dormitory - Wainoni
Accounts Payable --DFAT
Payment 1 - 20% Mobilization Payment for Labor based Contract
Payment 2 - 35% Payment for 50% of work
Payment 3 - 35% For completion of work
Payment 4 - 10% Retention
Labour Based Contract for Upgrade of Games Village for Pacific Games 2023 - GTB-GFC 09/22.
Lot 2 -King George Sixth National Secondary School Carpentry Works for Girls Dormitory - Wainoni
Accounts Payable --DFAT