Payment 1 - 20% Mobilization Payment for Labor based Contract
Payment 2 - 35% Payment for 50% of work
Payment 3 - 35% For completion of work
Payment 4 - 10% Retention
Labour Based Contract for Upgrade of Games Village for Pacific Games 2023 - GTB-GFC 09/22.
Lot 5 - St Nicholas College - Electrical works for Buildings 1 - 5, Classrooms & Building 6 - Ablution Blocks
Accounts Payable--DFAT
H & E Enterprise / National Hosting Authority - Honiara, Solomons Islands : National Hosting Authority, 2022-2023
Payment 1 - 20% Mobilization Payment for Labor based Contract
Payment 2 - 35% Payment for 50% of work
Payment 3 - 35% For completion of work
Payment 4 - 10% Retention
Labour Based Contract for Upgrade of Games Village for Pacific Games 2023 - GTB-GFC 09/22.
Lot 5 - St Nicholas College - Electrical works for Buildings 1 - 5, Classrooms & Building 6 - Ablution Blocks