NIU World Construction /
NIU World Construction /
National Hosting Authority
- Honiara, Solomons Islands : National Hosting Authority, 2022 - 2023
- Payment 1: (20%) Mobilisation
- Payment 2: (35%) Progress Payment
- Payment 3: (35%) Completion of Games village work at St. Nicholas college.
- Payment 4: (10%) Retention
Labour Based Contract for Upgrade of Games Village for Pacific Games 2023 - GTB-GFC 09/22.
Lot 5 -Saint Nicholas College - Carpentry Works for Building 1 - Classroom
Accounts Payable --DFAT
- Payment 1: (20%) Mobilisation
- Payment 2: (35%) Progress Payment
- Payment 3: (35%) Completion of Games village work at St. Nicholas college.
- Payment 4: (10%) Retention
Labour Based Contract for Upgrade of Games Village for Pacific Games 2023 - GTB-GFC 09/22.
Lot 5 -Saint Nicholas College - Carpentry Works for Building 1 - Classroom
Accounts Payable --DFAT