Mountol Enterprises / National Hosting Authority
Material type:
TextPublication details: Honiara, Solomons Islands : National Hosting Authority, 2023Subject(s):
| Item type | Current library | Collection | Call number | Materials specified | Status | Date due | Barcode | |
|---|---|---|---|---|---|---|---|---|
Folder
|
NHA Pacific Games 2023 Library | Secretariat | 2023 | Available |
Construction of New Guard House at DC Park for the Marine Sports Facility
LOT1 - Construction of Boat Storage Facility at DC Park For Marine Sports Facility
(GTB-GFC13/22)
-Payment 1: (50%) Mobilisation
-Payment 2: (20%) Progress Payment
-Payment 3: (25%) Construction of Boat storage construction.
-Payment 4: (5%) Retention.
-Variation 1: Extention of reinforce concrete slab at the end of the boat storage facility.
-Variation 2: Completion of all Work - Additional Electrical and Plumbing Works for the Boat storage at DC Park Marine Sports Facility.
There are no comments on this title.