BJ Engineering / National Hosting Authority - Honiara, Solomons Islands : National Hosting Authority, 2023

Labour-based contract for upgrade of Games Village for Pacific Games 2023
Don Bosco Institute of Technology - Electrical Works for Building 1 Classroom & Ablution - Mobilization Payment 1 - 20%
- Payment 2 - (35%) of total payment for 50% Completion of work
- Payment 3 - (35%) for Completion of work
-Retention payment 10% after satisfaction of 3 months defect liability period
- Variation 1 & 2 payments


Accounts Payable--DFAT Payment