3D Construction Ltd. / National Hosting Authority, - Honiara, Solomons Islands : National Hosting Authority, 2022-2023

Payment 1 - 20% Mobilization Payment for Labor based Contract
Payment 2 - 35% Payment for 50% of work done as per amended payment Schedule of the Contract
Payment 3 - 35% For completion of work
Payment 4 - Variation 1 - Additional carpentry works done to Building 3
Payment 5 - 10% Retention
Upgrade of Schools - GTB-GFC 09/22.
LOT 1 - Carpentry Works for Building 3 -Boys Dormitory &Classroom at St. Joseph Tenaru.


Accounts Payable --DFAT