AVCON Limited / National Hosting Authority, - Honiara, Solomons Islands : National Hosting Authority, 2022-2023

Payment 1 - 20% Mobilization Payment for Labor based Contract
Payment 2 - 35% Payment for 50% of work done as per Schedule of the Contract
Payment 3 - 35% For completion of work
Payment 4 - Variation 1 - Additional carpentry works
Payment 5 - 10% Retention

Upgrade of Games Village - GTB-GFC 09/22.

Lot 4 - Carpentry Works for SINU Kukum Campus - Hostel K206.


Accounts Payable --DFAT