PN General Construction. /
National Hosting Authority,
- Honiara, Solomons Islands : National Hosting Authority, 2022 - 2023
Payment 1: 20% Mobilisation Payment 2: 35% Progress payment for labour base contract- KGVI plumbing Payment 3: 35% Completion of labour contract for upgrade of Games Village for PG2023- Plumbing work KGVI. Variation 1: Plumbing work -KGVI School Building 11 & 12. Payment 4: 10% Retention.
Labour Based Contract for Upgrade of Games Village for Pacific Games 2023 - GTB-GFC 09/22. LOT 2 - King George VI National Secondary School - Plumbing Works for Wainoni & Graciosa Dormitories.